Project Kickoff 8/2000

Detailed work plan

Work Plan- Development & Implementation
Deliverables
Estimated Timeframe
Assigned To
Project Management
Create work Plan work plan 7/31/00-8/4/00 Project Manager
Staff Project staffing plan 8/7/00-8/11/00 Project Manager
Determine Standards project charter 8/7/00-8/11/00 Project Manager
Controlling and Directing Project   7/31/00-completion Project Manager
Software Development
User Interface Development      
  Phase 1 Prototype Development   8/21/00-9/1/00 Programmer
  Software Testing   9/4/00-9/7/00 Programmer
  User Feedback and Client sign off phase 1 client approval 9/8/00 Programmer and PM
  Phase 2 Prototype Development   9/11/00-9/22/00 Programmer
  Software Testing   9/25/00-9/28/00 Programmer
  User Feedback and Client sign off phase 2 client approval 9/29/00 Programmer and PM
  Phase 3 Prototype Development   10/2/00-10/13/00 Programmer
  Software Testing   10/15/00-10/19/00 Programmer
  User Feedback and final Client sign off phase 3 client approval 10/20/00 Programmer and PM
Database Development
 Phase 1 Development   9/4/00-9/24/00 Systems Analyst
 Testing and client sign off phase 1 client approval 9/25/00-9/29/00 Systems Analyst and PM
 Phase 2 Development   10/2/00-10/20/00 Systems Analyst
 Testing and client sign off phase 2 client approval 10/23/00-10/27/00 Systems Analyst and PM
 Disaster Recovery and backup procedures developed procedures specification 10/30/00-11/10/00 Systems Analyst
 Develop update procedures   10/30/00-11/10/00 Systems Analyst
 Importing Current Data into database   11/13/00-11/24/00 Systems Analyst and client
 Testing on live data (database capabilities and reliability)   11/27/00-12/8/00 Systems Analyst
 Client sign off on functionality database- client sign off 12/8/00 Systems Analyst and PM
Network Development
 Connecting system to associated systems and day care locations   10/02/00-11/24/00 Systems Analyst
Installation
 Installing system software at HQ   10/30/00-11/10/00 Progr. and Change Mgnt. A.
 Deploying software to day care locations   11/13/00-11/17 Progr. and Change Mgnt. A.
 Implementing Database   12/11/00-12/22/00 Sys. A. and Change Mgnt. A.
 Final Client Sign Off final client sign off 1/1/01 Project Manager
 System Go Live   1/8/01 Project Manager
Training
 End user training phase 1 (pre-implementation)   12/4/00-12/8/00 Change Mgnt. Analyst
 End user training phase 2 (pre-implementation)   12/18/00-12/22/00 Change Mgnt. Analyst
 End User support (post-implementation)   1/15/01-1/26/01 Change Mgnt. Analyst
Project Closure
 Internal Evaluation Group self evaluation document 1/19/01 Project Team
 Client Evaluation Client project evaluation document 1/19/01 Client
 Project Closure document Project Closure Document 1/26/01 Project Manager